Skip to main content

Scheduled completion...

We approached the builder into nailing down some dates for completion as they were closing in to the pointy end of the build. It seems all the major milestones are completed, ongoing or schedule to be started soon. That leaves all the minor fixings and installation. The builder have tentatively given us a practical completion date of the 18th of December. That is 2-3 days out from a scheduled Christmas shutdown that lasts two weeks. Prior to that we will have the final invoice processed a week before. This should enable the bank to organise a valuation so that they can process the final payment. Once final payment is received then handover can be made. If all goes smoothly, there's a chance that in those two days the bank can lodge payment and we will be ready to move in. If not, we will have to wait until after Christmas.
We then had a meeting on site in regards to concreting the driveway and other areas. We inspected the external finishings. We picked up that the meter-box was placed on the house instead of the outside the front fence. Once we told him our reasons for that, he then questioned whether a front gate was allowed. It was not on the inclusions list he was holding but was listed on the variations. He was surprised and mentioned it could hold up the whole completion plan. It seems like a whole lot of scrambling on their part as they want to completed the house by this year, but this whole gate issues has thrown a spanner in the works, he mentioned the cut off date for aluminium fencing was last week for jobs done before Christmas. He is scrambling and hopefully they can deliver. More news to come on this front.

Comments

Popular posts from this blog

Day 3 of Excavation

Well, they were back there for yet another day of rock breaking labour. It now looks flat and smooth. For some reason it, doesn't look like what we pictured. We picked up that the wall that they were going to build is a lot higher that we originally though. Made a complaint, and they will be back to fix the levels. See my son in one of the pictures, he is 7 is roughly 1.2metres tall. None of the walls are supposed to be more than 1metre tall. Not only does this make it more expensive, but engagement of engineers is required to properly design a retaining wall.

Filling Footings, and downstairs tiles grouted

Today they poured the footings ready for the block work to begin. Lower level floor got grouted.

Selections...

What a hectic week. The past few weekend has been driving from supplier to supplier to work out how we want the finish of the house to look. The builder has a few preferred suppliers for things such as appliances, tapware, electricals, cabinets, bricks, carpet, tiles etc. Since the builder is an independent builder, they do not have their own studio like most project builders have. For some of the selections we must visit a store before hand and select from the range of finishings so that the supplier can quote and once we are happy with the price, they will incorporate the fittings into kitchen/bathroom cabinets. So the builder would give us an allowance on most areas of the house, it was our responsibility to visit the store and spend the allowance. Our aim was to stay as close to that allowance as we could. If the spend was under the allowance, than the builder would keep the remaining amount, if we exceed the allowance, then we would have to pay the excess. The first place we o...