Today the render on the house and the walls got completed. We also discovered a few problems. Power had not been run to the electric fence opener, nor was a fence ordered. Seems like the supervisor missed it off the contract. It's a big frantic rush to get it made before Christmas. Also the meter was mistakenly installed on the side of the house. We asked specifically to be installed on the front fence to prevent any meter readings being done inside and have a need to leave the gates opened.
Today shrubs were planted and mulch laid. The flooring guy was here laying the underlay, tomorrow he does the carpet. No photos, cos I couldn't get in. What's Left 8 Days Paint to front of wall Stair/handrail polish final coats?? Door stained Outdoor kitchen fix up Rangehood cupboards Tile skirt behind toilet Landscaping cont' Fencing and Gate Clothesline Paint touch ups Blinds installed Tiler silicone Carpet