Today roof trusses on the garage and the outdoor area got installed. I'd say they need crane assistance with the main larger sections. Not even sure how OH&S is even allowing them up there without safety harnesses or even barriers at those heights.

From inside the Garage

Over the garage

Entrance

Our Balcony

Under the balcony

Left side of house

Dining

View from Backyard

Outdoor area

Windows from outdoor


Kitchen window from inside

Butlers Pantry window from inside

Entrance Hallway

Temporary Stairs

Kids Retreat/Study






Balcony


Master Ensuite




Right side of house



Comments

Popular posts from this blog

Day 3 of Excavation

Well, they were back there for yet another day of rock breaking labour. It now looks flat and smooth. For some reason it, doesn't look like what we pictured. We picked up that the wall that they were going to build is a lot higher that we originally though. Made a complaint, and they will be back to fix the levels. See my son in one of the pictures, he is 7 is roughly 1.2metres tall. None of the walls are supposed to be more than 1metre tall. Not only does this make it more expensive, but engagement of engineers is required to properly design a retaining wall.

Filling Footings, and downstairs tiles grouted

Today they poured the footings ready for the block work to begin. Lower level floor got grouted.

Selections...

What a hectic week. The past few weekend has been driving from supplier to supplier to work out how we want the finish of the house to look. The builder has a few preferred suppliers for things such as appliances, tapware, electricals, cabinets, bricks, carpet, tiles etc. Since the builder is an independent builder, they do not have their own studio like most project builders have. For some of the selections we must visit a store before hand and select from the range of finishings so that the supplier can quote and once we are happy with the price, they will incorporate the fittings into kitchen/bathroom cabinets. So the builder would give us an allowance on most areas of the house, it was our responsibility to visit the store and spend the allowance. Our aim was to stay as close to that allowance as we could. If the spend was under the allowance, than the builder would keep the remaining amount, if we exceed the allowance, then we would have to pay the excess. The first place we o...