Paint progress

Hasn't been much update recently, as painters and plasterers have been backwards and forwards having each others fix and inspect so that they are happy with the quality of finish before the painter puts the finishing colour on the top. Nothing worse than having imperfections underneath which show through once paint has been applied, the even colour makes it easier for faults to standout. Today I discovered the ceiling has been painted. External painting has completed on the top level, so they have moved into the internal part of the house. Looks like they have sprayed. Not sure how many coats, but I'm sure I agreed to a 3 coat system, ie. undercoat and two top coats.

Preparing for painting

Gaps in the dry wall have been filled, sanded back ready for painting. Safety switches installed, electricals are all located.

Minor updates

Not sure what has happened since the last post, but I've noticed a few extra details that have been a pleasant surprise, as we hadn't been aware they were included.  

Doors done and cabinets

Today doors got finished, and kitchen and bathroom cabinets went in. Today we are due for yet another progress payment. Roughly 12 weeks until completion.

Doors going in...

Today doors started going in.

Cladding complete and more internal progress

The external cladding has been completed with soffits, and drywall plastering has been fully sanded, cornices being installed.