Skip to main content

Decisions, decisions...

We spent weeks looking at display homes, talking to builders, looking at house design options. Since we had been through the process before we knew what we were looking for. We attended the display village at Rochedale estates just about every weekend. We visited builders such as GJ Gardner, Clarendon, Macarthy Homes, Metricon, Plantation Homes. We had built with Metricon last time, so this time the options were either Metricon or Plantation. Little did we know there would be another player coming to the party. They were an independent builder, we thought nothing of them, because we knew they were going to be more expensive, since they always are, but we had them along for the ride just for our curiosity. This builder is Landmark Homes, located out bayside Brisbane. The reason we considered them, was because they could give us an affordable turn-key package which sparked our interest.

After weeks of negotiations, we decided to go with Landmark Homes for several reasons, and it wasn't an easy decision, since we had shortlisted the builders down to Plantation and Landmark. Landmark's prices were all over the place. Some of our requests for design changes were also missed so we couldn't build confidence in them at the time. But their build time was attractive to us. Since we were renting this becomes a factor, since you don't want to be renting longer than you should, and the earlier you can build the better it will be for us.

We spent most of November and December deciding on making this big decision. We were almost committed to Plantation. Luckily during Christmas we had enough time to think it through. We looked at online reviews of all builders. A friend sent me to a website called undercover architect, which coincidentally enough, had a couple that was on a similar journey to us (albeit a couple of years before us) and had built with Landmark too. After reading this it gave us greater confidence in our decision  We were set on a design that we were happy with through Landmark Homes. We signed on the 18th of January 2018. We would be lucky to be moving in by June, but we have reserved the completion date until July, which we think is an achievable date.




Comments

Post a Comment

Popular posts from this blog

Day 3 of Excavation

Well, they were back there for yet another day of rock breaking labour. It now looks flat and smooth. For some reason it, doesn't look like what we pictured. We picked up that the wall that they were going to build is a lot higher that we originally though. Made a complaint, and they will be back to fix the levels. See my son in one of the pictures, he is 7 is roughly 1.2metres tall. None of the walls are supposed to be more than 1metre tall. Not only does this make it more expensive, but engagement of engineers is required to properly design a retaining wall.

Filling Footings, and downstairs tiles grouted

Today they poured the footings ready for the block work to begin. Lower level floor got grouted.

Selections...

What a hectic week. The past few weekend has been driving from supplier to supplier to work out how we want the finish of the house to look. The builder has a few preferred suppliers for things such as appliances, tapware, electricals, cabinets, bricks, carpet, tiles etc. Since the builder is an independent builder, they do not have their own studio like most project builders have. For some of the selections we must visit a store before hand and select from the range of finishings so that the supplier can quote and once we are happy with the price, they will incorporate the fittings into kitchen/bathroom cabinets. So the builder would give us an allowance on most areas of the house, it was our responsibility to visit the store and spend the allowance. Our aim was to stay as close to that allowance as we could. If the spend was under the allowance, than the builder would keep the remaining amount, if we exceed the allowance, then we would have to pay the excess. The first place we o...