More progress today with fitout of applicances. I already see a few things not right. 1. Oven doesn't quite fit in the hole; some mods to do here 2. BBQ in but side burner not quite right, caesarstone to be modified
Plumbers have been back at it, toilets installed, tap ware, drain, showers etc. Can't wait to use them. The hose on the showerhead looks a bit ordinary. Plenty of loo's in the house of Lu.
Today the concreters made an early start, forming the driveway, stairs and paths around the house. Can't get an appreciation for the colour of the exposed aggregate until it dries. Loving the wide driveway. We should be able to fit 4 extra vehicles in the drive with the gate open. the concreters will be back to cut and seal the concrete and that will complete their job.
Today plumbing fitout was started, a bit of draining in the front and all the plumbing supplies arrived. We also delivered the electrical appliances on the weekend.