More walls and cladding August 31, 2018 Internal wall plaster has been sanded down, and external cladding arrived. Scaffolding started to be erected for cladding and external painting. Read more
We have reached lock up... almost. August 29, 2018 Today we reached enclosed stage. Internal doors arrived and patch work continues. Read more
Internal and external walls continue August 28, 2018 Internally the walls got patched, and brick work on the outside continues to climb. Read more
Drywall stalls, bricks continue August 27, 2018 Bricks continue to be laid, and internal walls stop. At least one side of the house is done. Read more
Bricks stall, but walls continue August 24, 2018 Nothing got done externally, but internally more drywall got installed Read more
Bricking started August 22, 2018 Today the brickies arrived and started laying the brick work. Read more
More walls August 21, 2018 More of the walls got put in and starting to take shape internally Read more
Drywall and Arrival of Bricks August 20, 2018 Drywall got started today. Now you can actually get a feel for how the rooms feel. Bricks have arrived. Read more